Line 4 re-tendered without Sinhagad Road: what the 14 November notice says

On 14 November 2026 Maha-Metro re-issued the civil tender meant to build the metro along Sinhagad Road. The new notice covers the Line 4A spur only. The eight stations planned on this road are not in it.

Venkatesh Skydove Sales · 23 November 2026 · 5 min read

The June 2026 metro tender for Sinhagad Road and Line 4A beside the November re-tender for Line 4A only

On 14 November 2026 Maha-Metro re-issued the civil tender that was meant to build the metro along Sinhagad Road. The new notice covers the Line 4A spur only.

The eight stations planned on this road, from Dandekar Pul to Khadakwasla, are not in it. As of 25 November 2026, nothing else on Maha-Metro’s tenders page covers them either.

What the two notices say

The June 2026 package, P2-C03/2026, had two parts. The first was the viaduct from Dandekar Pul to Khadakwasla, 9.675 km with eight elevated stations. The second was Line 4A from SNDT College to Manik Baug, 7.247 km with six stations. Its deadline moved again and again: the first was 24 August 2026, and by early November it had reached 30 December 2026, reported as the eighth extension.

The notice dated 14 November 2026, P2-C03(R)/2026, describes one job: an elevated viaduct of 6.465 km with six stations on Line 4A from SNDT College to Manik Baug, including first-level flyovers at Karve Putala Chowk and Ambedkar Chowk. Bids are due on 31 December 2026 and open on 1 January 2027.

The June 2026 metro tender for Sinhagad Road and Line 4A beside the November re-tender for Line 4A only
The June package and the November re-tender, as Maha-Metro's tenders page lists them. · Illustration

We checked every list on the page: active tenders, tenders under process and awarded tenders. The June package is no longer on any of them, and no other civil package names Dandekar Pul to Khadakwasla.

What the notice does not say

Why. The tenders page gives no reason, and we have not found an official statement that does. So this site does not offer one.

What is on record is the background. In July 2026 Maha-Metro extended the bid deadline while it waited for the city’s final design for the High-Capacity Mass Transit Route, a planned elevated road that crosses and runs beside the metro. In September the city planned separate pillars for the two at Dandekar Bridge chowk, exactly where this stretch begins, and Maha-Metro said it could not decide until the city committed to paying for the flyovers involved. The Mayor has also asked for the metro to move to the riverbed or the canal road, and on 3 November 2026 Maha-Metro said the line would largely follow the existing road but that the idea could be considered. Any of these could explain a pause. None is confirmed as the reason for this one.

What it changes for a buyer

The June tender gave the contractor 42 months to build the viaduct and stations. That clock starts at the award, and there is now nothing to award for this road. Every estimate of when trains might run here, including our own arithmetic in the piece on Line 4, moves out by however long a fresh tender takes.

Some things do not move. Foundations for 39 of the 105 planned metro pillars went in with the flyover works and are still there. The flyover is open and you can drive it today. And Line 4A ends at Manik Baug, which is on Sinhagad Road, so the spur that is out to tender still reaches this corridor.

On a fifteen-year view the metro is still a fair reason to like this road. On any shorter view, this notice is one more reason not to pay a premium for it today. The ladder in the piece on infrastructure promises puts the Sinhagad Road stretch where it was before June: sanctioned, and not yet tendered.

How to watch for the next step

Maha-Metro’s tenders page lists each civil package with its scope and its dates. Look for a package that names Dandekar Pul to Khadakwasla. When one appears, this stretch is back on the clock, and we will update this page and the Line 4 piece the same week.

If a sales conversation gives you a completion year for the Sinhagad Road metro before then, ask which tender it comes from. As of 25 November 2026, there isn’t one.

More updates

All updates
The record at Navale Bridge: the November 2025 crash, eight years of police data, deaths in 2026 and the promised fixes

The Corridor

Navale Bridge, one year on: the black spot at the highway end of Sinhagad Road

Eight people died at Navale Bridge on 13 November 2025, and a list of fixes was promised within six months. A year later, here is what was promised, what the record shows, and what a buyer should do with it.

16 November 2026 · 6 min read

Navale Bridge, one year on: the black spot at the highway end of Sinhagad Road
Four websites quoting four different per square foot rates for Sinhagad Road

The Corridor

Sinhagad Road property rates in 2026, and why every site gives a different number

Four websites quoted four rates for the same road, and the highest was nearly double the lowest. By November 2026 one stretch alone spanned more than that. What is being measured, and the one figure that is not an estimate.

10 August 2026 · 7 min read

Sinhagad Road property rates in 2026, and why every site gives a different number

Be first when the numbers land

Carpet areas, the price list and the floor plans go to registered buyers before they reach the portals.

Call Now

Enquiry

Share your details and our team will get back to you.

By submitting you consent to be contacted about this project, including on a number registered with the National Do Not Call Registry.