Line 4 re-tendered without Sinhagad Road: what the 14 November notice says
On 14 November 2026 Maha-Metro re-issued the civil tender meant to build the metro along Sinhagad Road. The new notice covers the Line 4A spur only. The eight stations planned on this road are not in it.
Venkatesh Skydove Sales · 23 November 2026 · 5 min read
On 14 November 2026 Maha-Metro re-issued the civil tender that was meant to build the metro along Sinhagad Road. The new notice covers the Line 4A spur only.
The eight stations planned on this road, from Dandekar Pul to Khadakwasla, are not in it. As of 25 November 2026, nothing else on Maha-Metro’s tenders page covers them either.
What the two notices say
The June 2026 package, P2-C03/2026, had two parts. The first was the viaduct from Dandekar Pul to Khadakwasla, 9.675 km with eight elevated stations. The second was Line 4A from SNDT College to Manik Baug, 7.247 km with six stations. Its deadline moved again and again: the first was 24 August 2026, and by early November it had reached 30 December 2026, reported as the eighth extension.
The notice dated 14 November 2026, P2-C03(R)/2026, describes one job: an elevated viaduct of 6.465 km with six stations on Line 4A from SNDT College to Manik Baug, including first-level flyovers at Karve Putala Chowk and Ambedkar Chowk. Bids are due on 31 December 2026 and open on 1 January 2027.
The June package and the November re-tender, as Maha-Metro's tenders page lists them. · Illustration
We checked every list on the page: active tenders, tenders under process and awarded tenders. The June package is no longer on any of them, and no other civil package names Dandekar Pul to Khadakwasla.
What the notice does not say
Why. The tenders page gives no reason, and we have not found an official statement that does. So this site does not offer one.
What is on record is the background. In July 2026 Maha-Metro extended the bid deadline while it waited for the city’s final design for the High-Capacity Mass Transit Route, a planned elevated road that crosses and runs beside the metro. In September the city planned separate pillars for the two at Dandekar Bridge chowk, exactly where this stretch begins, and Maha-Metro said it could not decide until the city committed to paying for the flyovers involved. The Mayor has also asked for the metro to move to the riverbed or the canal road, and on 3 November 2026 Maha-Metro said the line would largely follow the existing road but that the idea could be considered. Any of these could explain a pause. None is confirmed as the reason for this one.
What it changes for a buyer
The June tender gave the contractor 42 months to build the viaduct and stations. That clock starts at the award, and there is now nothing to award for this road. Every estimate of when trains might run here, including our own arithmetic in the piece on Line 4, moves out by however long a fresh tender takes.
Some things do not move. Foundations for 39 of the 105 planned metro pillars went in with the flyover works and are still there. The flyover is open and you can drive it today. And Line 4A ends at Manik Baug, which is on Sinhagad Road, so the spur that is out to tender still reaches this corridor.
On a fifteen-year view the metro is still a fair reason to like this road. On any shorter view, this notice is one more reason not to pay a premium for it today. The ladder in the piece on infrastructure promises puts the Sinhagad Road stretch where it was before June: sanctioned, and not yet tendered.
How to watch for the next step
Maha-Metro’s tenders page lists each civil package with its scope and its dates. Look for a package that names Dandekar Pul to Khadakwasla. When one appears, this stretch is back on the clock, and we will update this page and the Line 4 piece the same week.
If a sales conversation gives you a completion year for the Sinhagad Road metro before then, ask which tender it comes from. As of 25 November 2026, there isn’t one.
Navale Bridge, one year on: the black spot at the highway end of Sinhagad Road
Eight people died at Navale Bridge on 13 November 2025, and a list of fixes was promised within six months. A year later, here is what was promised, what the record shows, and what a buyer should do with it.
The Sun City to Karvenagar bridge: a second river crossing, now due in January 2027
A 279 metre bridge over the Mutha would give this side of Sinhagad Road a second way across to Karvenagar. It has had five opening dates and missed four. Here is where it stands.
Sinhagad Road property rates in 2026, and why every site gives a different number
Four websites quoted four rates for the same road, and the highest was nearly double the lowest. By November 2026 one stretch alone spanned more than that. What is being measured, and the one figure that is not an estimate.