The Sun City to Karvenagar bridge: a second river crossing, now due in January 2027
A 279 metre bridge over the Mutha would give this side of Sinhagad Road a second way across to Karvenagar. It has had five opening dates and missed four. Here is where it stands.
Venkatesh Skydove Sales · 12 November 2026 · 5 min read
For most of its length Sinhagad Road runs beside the Mutha, and there are not many ways across it. A new one has been under construction between Sun City and Karvenagar for about two years.
It has had five opening dates. Four have passed. The current one is January 2027.
What is being built
A bridge over the Mutha, 279 metres long and 30 metres wide on nine spans, built by the Pune Municipal Corporation at about ₹44.86 crore. That is the February 2026 figure. A 2025 report gave ₹32.56 crore, so the cost has moved along with the dates.
It joins Sun City, on the Sinhagad Road bank, to Karvenagar on the other side. Punekar News puts the detour it removes at around three kilometres.
Five dates
March 2025. The deadline at the time, with the work reported as only 54 per cent complete.
End of April 2026. In February 2026 Dinkar Gojare, head of the corporation’s special projects department, said: “we are aiming to complete the entire project by the end of April.”
26 May 2026. A pre-monsoon deadline reported in March. By 1 May the April target was reported missed.
About October 2026. In mid-July the project was reported about 80 per cent complete, with the corporation aiming to open it “within the next two-and-a-half months.”
January 2027. On 2 October 2026 the remaining work was expected to finish by December, with the bridge likely to open to traffic in January. The connecting road on the Karvenagar side was complete. The approach road on the Sun City side was still being built.
Each opening target and the report that set it. The bridge was not open on the date of this article. · Illustration
Why a second crossing matters here
Much of this corridor’s morning traffic is not going into town. It is going west, across the river. In August 2026, reporting on the flyover’s first year found that most of the morning flow was headed for Karve Nagar and that Rajaram Bridge, the existing crossing, was the choke point. More on that in the piece on the flyover.
A second bridge towards Karvenagar takes some of that load off a single point. It will not fix the corridor, and nobody serious claims it will. It does give the households on this stretch a choice they do not have today.
What to do with it as a buyer
Do not price it in yet. Four dates have come and gone, and a bridge that opens in January is still a bridge that is not open in November. The day you can drive across it, it counts.
Whether it matters to a particular home depends on where the home is, and on where your days go. If they run west to Karvenagar, Kothrud or Warje, it could matter a great deal. If they run into the city or out to the highway, much less.
For Skydove that question has to wait. No plot location has been published, which is why this site publishes no distance table. When the address is out, this bridge is one of the first things worth measuring from it.
Line 4 re-tendered without Sinhagad Road: what the 14 November notice says
On 14 November 2026 Maha-Metro re-issued the civil tender meant to build the metro along Sinhagad Road. The new notice covers the Line 4A spur only. The eight stations planned on this road are not in it.
Navale Bridge, one year on: the black spot at the highway end of Sinhagad Road
Eight people died at Navale Bridge on 13 November 2025, and a list of fixes was promised within six months. A year later, here is what was promised, what the record shows, and what a buyer should do with it.
Sinhagad Road property rates in 2026, and why every site gives a different number
Four websites quoted four rates for the same road, and the highest was nearly double the lowest. By November 2026 one stretch alone spanned more than that. What is being measured, and the one figure that is not an estimate.